Electricity Status Update From EDF

KevinS

Senior Insider
EDF (Électricité de France), the French Electricity Utility, has posted the following update:



Power Situation Stabilized Before Thanksgiving

Since October 20, 2026, EDF Group teams have been mobilized to address the production shortfall affecting the Saint-Barthélemy power grid and to maintain the island's power supply as much as possible.

EXCEPTIONAL RESOURCES DEPLOYED

Following a new record for electricity consumption on October 28, 2026, EDF continues to deploy exceptional resources to guarantee Saint-Barthélemy's power supply and limit the impact on customers.

To bolster production capacity and secure the island's power supply, EDF mobilized significant human and material resources immediately after the failure of one of our most powerful generators:

• 11 generators are already deployed across the island, providing electricity to residents;

• Specialized reinforcements comprised of logistics experts, mechanics, and electricians are working with local teams to accelerate the restoration of generating units and ensure the installation and commissioning of generators;

• Demand response mechanisms for customers with significant capacity for adjustment continue to be activated.

Thanks to all these measures, no widespread load shedding has occurred since October 23, 2026, except for November 2, when a temporary load shedding affecting 400 customers for a period of two hours was reported.

EXEMPLARY COLLECTIVE MOBILIZATION

EDF wishes to acknowledge the ongoing commitment of the Collectivity of Saint-Barthélemy, which has supported the teams since the beginning of this crisis.

Its support has notably facilitated the transport of heavy equipment to the island, identified suitable locations for installing generators, and assisted with their connection to the electrical grid.

EDF also thanks all the public services, businesses, partners, and residents who are contributing to this collective effort.

ECO-FRIENDLY PRACTICES REMAIN ESSENTIAL

Despite the additional resources deployed, controlling electricity consumption remains a crucial lever, now and in the future, for maintaining the system's balance, particularly during peak hours.

EDF encourages everyone to continue practicing energy conservation:

• limit the simultaneous use of the most energy-intensive appliances;

• reduce the use of air conditioning whenever possible;

• schedule certain electrical uses outside of peak hours;

• optimize the operation of non-essential equipment.

Every action counts and contributes to strengthening the island's energy security.

RETURN TO NORMAL EXPECTED BY MID-NOVEMBER

EDF teams are continuing their efforts to restore power generation as soon as possible.

Thanks to this mobilization, a return to normal is expected by mid-November.

EDF will continue to provide regular updates on the situation and thanks the public for their understanding, trust, and cooperation.
 
EDF (Électricité de France), the French Electricity Utility, has posted the following update:



Power Situation Stabilized Before Thanksgiving

Since October 20, 2026, EDF Group teams have been mobilized to address the production shortfall affecting the Saint-Barthélemy power grid and to maintain the island's power supply as much as possible.

EXCEPTIONAL RESOURCES DEPLOYED

Following a new record for electricity consumption on October 28, 2026, EDF continues to deploy exceptional resources to guarantee Saint-Barthélemy's power supply and limit the impact on customers.

To bolster production capacity and secure the island's power supply, EDF mobilized significant human and material resources immediately after the failure of one of our most powerful generators:

• 11 generators are already deployed across the island, providing electricity to residents;

• Specialized reinforcements comprised of logistics experts, mechanics, and electricians are working with local teams to accelerate the restoration of generating units and ensure the installation and commissioning of generators;

• Demand response mechanisms for customers with significant capacity for adjustment continue to be activated.

Thanks to all these measures, no widespread load shedding has occurred since October 23, 2026, except for November 2, when a temporary load shedding affecting 400 customers for a period of two hours was reported.

EXEMPLARY COLLECTIVE MOBILIZATION

EDF wishes to acknowledge the ongoing commitment of the Collectivity of Saint-Barthélemy, which has supported the teams since the beginning of this crisis.

Its support has notably facilitated the transport of heavy equipment to the island, identified suitable locations for installing generators, and assisted with their connection to the electrical grid.

EDF also thanks all the public services, businesses, partners, and residents who are contributing to this collective effort.

ECO-FRIENDLY PRACTICES REMAIN ESSENTIAL

Despite the additional resources deployed, controlling electricity consumption remains a crucial lever, now and in the future, for maintaining the system's balance, particularly during peak hours.

EDF encourages everyone to continue practicing energy conservation:

• limit the simultaneous use of the most energy-intensive appliances;

• reduce the use of air conditioning whenever possible;

• schedule certain electrical uses outside of peak hours;

• optimize the operation of non-essential equipment.

Every action counts and contributes to strengthening the island's energy security.

RETURN TO NORMAL EXPECTED BY MID-NOVEMBER

EDF teams are continuing their efforts to restore power generation as soon as possible.

Thanks to this mobilization, a return to normal is expected by mid-November.

EDF will continue to provide regular updates on the situation and thanks the public for their understanding, trust, and cooperation.
I hope the optimism of this report translates to reality.
 
Thank you for the explanation. I hope the power grid can handle the popularity of this beloved island. Even in California, we try to be conservative when we use our optional appliances, trying for off hours if possible, but our electricity costs just doubled, especially during our very unusual hot spell for a couple of months this Summer/Fall. Hopefully, people will do the best they can to help the situation 🙏 Also hoping the hotels can ask their guests to only use the A/C when necessary..
 
6908.jpg
 
There was a similar view last night from Marigot Bay about 12:25 when electricity in the ‘hood went off ‘til 3:45 . . . I say “similar” because as I looked across the Bay, Mont Jean was lit up like a bright Christmas tree. I don’t know if homes there have private generators or were in an unaffected “sector.” Or both?
 
IMG_8351.jpeg
The Stadium may use more electricity than a Texas Data Center. Extraordinarily bright well into the night.
 
New consumption record during off season ? Hmmm


I was following a local Facebook group where there was a pretty heated discussion about the island's electricity consumption, particularly the energy wasted by large, unoccupied villas. Some of the practices described were eye-opening: villas with standing instructions to keep A/C running in every room, heated swimming pools, and, most interestingly, heated floors while the A/C is set to 20°!

I think the island could do a lot more to encourage energy conservation among large consumers, as well as promote greater use of renewable energy, solar pool heating and solar panels for electricity.

St. Barth certainly isn't short of sunshine!
 
Our power was out from midnight to 2am and again from 7.15-9.15am this morning - the power outages cut power to the water plant so by about 8am the reservoirs in Vitet and Colombier were empty so no city water, and no power for the cistern pump...
 
*⚡ SAINT-BARTHÉLEMY: PROVISIONAL POWER OUTAGE SCHEDULE*

*📅 Sunday, November 8, 2026*

Due to ongoing strain on electricity production, power outages may be necessary to maintain grid stability.

⚠️ This schedule is provisional. Outages are not systematic and depend on available production and the island's actual consumption.

📋 See below for the times and areas likely to be affected.

*🕗 FROM 8 AM TO 11 AM – SAINT-JEAN, LORIENT, EAST COAST, AND GUSTAVIA SECTORS*

• *Saint-Jean and Lorient Sector:* Lédée housing development, Super U supermarket, airport, La Savane shopping center, Saint-Jean main road, Les Sables shopping center, Vaval center, Les Amandiers center, Villa Créole, Les Jardins de Saint-Jean, Jean Barth residences, Espace Neptune, Coupe-Gorge road, Lorient Ti Fond, L’Îlot shopping center, and L’Oasis shopping center.

• *Lorient and East Coast Sector:* Lorient Centre Road, Post Office, Traffic Department, Monoprix, Jojo Burger, road to Petite Saline, Ligne de Saint-Barth cul-de-sac, vehicle inspection center, Morne Finistère, Pointe Milou, Grand Carénage, Mont Jean, Mono-Shop, Marigot La Cave and Marigot Bord de Mer.

• *Gustavia Sector:* Capitaine Bertin building, Carré d’Or building, À Vos Marques building, Pablo building, CPS, sub-prefecture, Colony Club, Couchant subdivision, Lubin Brin Street, section of Fahlberg Street before L’Ancre, Lurin Road, Pogammus subdivision, Chemin des Plateaux, Gouverneur Road, Andres subdivision and educational farm.

*🕚 FROM 11 AM TO 3 PM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux sports field, territorial swimming pool, Saint-Jean Pond road, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing development, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Petit Cul-de-Sac Pond area, Le Levant housing development, Grand Cul-de-Sac heights, and Grand Cul-de-Sac Pond road.

• *Marigot Sector:* STIS, morgue, gas station, Galeries du Commerce and Mangliers shopping areas, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

*🕒 FROM 3 PM TO 6:30 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

*🕡 FROM 6:30 PM TO 11:00 PM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux, territorial swimming pool, Route de l’Étang de Saint-Jean, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing development, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Étang de Petit Cul-de-Sac area, Le Levant housing development, Grand Cul-de-Sac heights, and Route de l’Étang de Grand Cul-de-Sac.

• *Marigot Sector:* STIS, morgue, gas station, shopping areas of Galeries du Commerce and Mangliers, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

_⚡ Let's continue our efforts to conserve energy! Limiting our consumption helps reduce the risk of power outages._

_🙏 Thank you all for your support and understanding._
 
Fuel delivery, from Pesident Xavier Kedee:


This Sunday, I exceptionally requested that the Port Director, Mr. Frédéric Blanchard, open the port facilities to receive a tanker.

This delivery ensures the island's fuel supply, which is essential during this period of strain on the electricity grid.

Despite challenging sea and weather conditions, the operations proceeded smoothly.

Thank you to the port teams for their dedication to public service and their hard work today.

Have a good rest of the weekend, everyone.
 
⚡ *SAINT-BARTHÉLEMY: PROVISIONAL POWER SHEDDING SCHEDULE*

📅 *Monday, November 9, 2026*

Due to ongoing strain on electricity production, power cuts may be necessary to maintain grid stability.

⚠️ This schedule is provisional. Power cuts are not systematic and depend on available production and the island's actual consumption.

📋 See below for the times and areas likely to be affected.

🕗 *FROM 8 AM TO 11 AM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux sports field, territorial swimming pool, Saint-Jean Pond road, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing development, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Petit Cul-de-Sac Pond area, Le Levant housing development, Grand Cul-de-Sac heights, and Grand Cul-de-Sac Pond road.

• *Marigot Sector:* STIS, morgue, gas station, Galeries du Commerce and Mangliers shopping centers, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

🕚 *FROM 11 AM TO 3 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

🕒 *FROM 3 PM TO 6:30 PM – SAINT-JEAN, LORIENT, EAST COAST AND GUSTAVIA AREAS*

• *Saint-Jean and Lorient Area:* Lédée housing estate, Super U supermarket, airport, La Savane shopping center, Saint-Jean main road, Les Sables shopping center, Vaval center, Les Amandiers center, Villa Créole, Les Jardins de Saint-Jean, Jean Barth residences, Espace Neptune, Coupe-Gorge road, Lorient Ti Fond, L’Îlot shopping center and L’Oasis shopping center.

• *Lorient and East Coast Sector:* Lorient Centre Road, Post Office, Traffic Department, Monoprix, Jojo Burger, road to Petite Saline, Ligne de Saint-Barth cul-de-sac, vehicle inspection center, Morne Finistère, Pointe Milou, Grand Carénage, Mont Jean, Mono-Shop, Marigot La Cave and Marigot Bord de Mer.

• *Gustavia Sector:* Capitaine Bertin building, Carré d’Or building, À Vos Marques building, Pablo building, CPS, sub-prefecture, Colony Club, Couchant subdivision, Lubin Brin Street, section of Fahlberg Street before L’Ancre, Lurin Road, Pogammus subdivision, Chemin des Plateaux, Gouverneur Road, Andres subdivision and educational farm.

🕡 *FROM 6:30 PM TO 11:00 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

⚡ _Let's continue our efforts to conserve energy! Limiting our consumption helps reduce the risk of power outages._

🙏 _Thank you all for your cooperation and understanding._
 
*⚡ SAINT-BARTHÉLEMY: PROVISIONAL POWER OUTAGE SCHEDULE*

*📅 Thursday, November 12, 2026*

Due to ongoing strain on electricity production, power outages may be necessary to maintain grid stability.

⚠️ This schedule is provisional. Outages are not systematic and depend on available production and the island's actual consumption.

📋 See below for the times and areas likely to be affected.

*🕗 FROM 8 AM TO 11 AM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

*🕚 FROM 11 AM TO 3 PM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux sports field, territorial swimming pool, Saint-Jean Pond road, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing development, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Petit Cul-de-Sac Pond area, Le Levant housing development, Grand Cul-de-Sac heights, and Grand Cul-de-Sac Pond road.

• *Marigot Sector:* STIS, morgue, gas station, Galeries du Commerce and Mangliers shopping areas, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

*🕒 FROM 3 PM TO 6:30 PM – SAINT-JEAN, LORIENT, EAST COAST, AND GUSTAVIA AREAS*

• *Saint-Jean and Lorient Area:* Lédée housing development, Super U supermarket, airport, La Savane shopping center, Saint-Jean main road, Les Sables shopping center, Vaval center, Les Amandiers center, Villa Créole, Les Jardins de Saint-Jean, Jean Barth residences, Espace Neptune, Coupe-Gorge road, Lorient Ti Fond, L’Îlot shopping center, and L’Oasis shopping center.

• *Lorient and East Coast Sector:* Lorient Centre Road, Post Office, Traffic Department, Monoprix, Jojo Burger, road to Petite Saline, Ligne de Saint-Barth cul-de-sac, vehicle inspection center, Morne Finistère, Pointe Milou, Grand Carénage, Mont Jean, Mono-Shop, Marigot La Cave and Marigot Bord de Mer.

• *Gustavia Sector:* Capitaine Bertin building, Carré d’Or building, À Vos Marques building, Pablo building, CPS, sub-prefecture, Colony Club, Couchant subdivision, Lubin Brin Street, section of Fahlberg Street before L’Ancre, Lurin Road, Pogammus subdivision, Chemin des Plateaux, Gouverneur Road, Andres subdivision and educational farm.

*🕡 FROM 6:30 PM TO 11:00 PM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux, territorial swimming pool, Route de l’Étang de Saint-Jean, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing development, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Étang de Petit Cul-de-Sac area, Le Levant housing development, Grand Cul-de-Sac heights, and Route de l’Étang de Grand Cul-de-Sac.

• *Marigot Sector:* STIS, morgue, gas station, shopping areas of Galeries du Commerce and Mangliers, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

_⚡ Let's continue our efforts to conserve energy! Limiting our consumption helps reduce the risk of power outages._

_🙏 Thank you all for your support and understanding._
 
⚡ *SAINT-BARTHÉLEMY: PROVISIONAL POWER SHEDDING SCHEDULE*
📅 *Friday, November 13, 2026*

Due to ongoing strain on electricity production, power cuts may be necessary to maintain grid stability.

⚠️ This schedule is provisional. Power cuts are not systematic and depend on available production and the island's actual consumption.

📋 See below for the times and areas likely to be affected.

🕗 *FROM 8 AM TO 11 AM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux sports field, territorial swimming pool, Saint-Jean Pond road, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing development, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Petit Cul-de-Sac Pond area, Le Levant housing development, Grand Cul-de-Sac heights, and Grand Cul-de-Sac Pond road.

• *Marigot Sector:* STIS, morgue, gas station, Galeries du Commerce and Mangliers shopping centers, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

🕚 *FROM 11 AM TO 3 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

🕒 *FROM 3 PM TO 6:30 PM – SAINT-JEAN, LORIENT, EAST COAST AND GUSTAVIA AREAS*

• *Saint-Jean and Lorient Area:* Lédée housing estate, Super U supermarket, airport, La Savane shopping center, Saint-Jean main road, Les Sables shopping center, Vaval center, Les Amandiers center, Villa Créole, Les Jardins de Saint-Jean, Jean Barth residences, Espace Neptune, Coupe-Gorge road, Lorient Ti Fond, L’Îlot shopping center and L’Oasis shopping center.

• *Lorient and East Coast Sector:* Lorient Centre Road, Post Office, Traffic Department, Monoprix, Jojo Burger, road to Petite Saline, Ligne de Saint-Barth cul-de-sac, vehicle inspection center, Morne Finistère, Pointe Milou, Grand Carénage, Mont Jean, Mono-Shop, Marigot La Cave and Marigot Bord de Mer.

• *Gustavia Sector:* Capitaine Bertin building, Carré d’Or building, À Vos Marques building, Pablo building, CPS, sub-prefecture, Colony Club, Couchant subdivision, Lubin Brin Street, section of Fahlberg Street before L’Ancre, Lurin Road, Pogammus subdivision, Chemin des Plateaux, Gouverneur Road, Andres subdivision and educational farm.

🕡 *FROM 6:30 PM TO 11:00 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

⚡ _Let's continue our efforts to conserve energy! Limiting our consumption helps reduce the risk of power outages._

🙏 _Thank you all for your cooperation and understanding._
 