Electricity Status Update From EDF

This is by the stadium.
 

Attachments

  • IMG_4037.jpeg
    IMG_4037.jpeg
    112.7 KB · Views: 47
Looking at the continuing construction (did somebody promised to slow it down?) St Barth will soon need to buy/rent floating nuclear station(s)
 
my understanding was that generators (EDF responsibility) are old and failed rather than overloaded ?
Is that correct ?
 
My understanding is that two of the large EDF generators, G7 and G8 (8MW each), are down. The G8 generator is down for a month-long period of preventative maintenance, and is expected to return to service this week. The G7 generator failed and is being repaired, but I haven’t heard an expected completion date.

I’ve lost track of how many generators are in the EDF plant in Public. Total daily power usage is somewhere around 24MW, so there must be more generators than just G7 and G8, but likely with lower capacity.

There are a number (10+?) of smaller temporary generators which EDF has had shipped in, and which are placed in locations around the island. I don’t know details on the types and sizes of the temporary generators. If they’re Continuous or Prime Power then they’re designed to run non-stop for months. If they’re Standby Power then they’ll have different duty hour specifications and maintenance requirements.
 
I've been wondering as I watch these posts: Is there a case to be made for solar? I mean, oil: not plentiful on-island; sunshine: plentiful, even more so during the dry (ie, tourist) season. Clearly that's not a solution to this week's need, but long-term? It seems so obvious to me that there must be some reasons-why-not that I'm not aware of.....
 
I've been wondering as I watch these posts: Is there a case to be made for solar? I mean, oil: not plentiful on-island; sunshine: plentiful, even more so during the dry (ie, tourist) season. Clearly that's not a solution to this week's need, but long-term? It seems so obvious to me that there must be some reasons-why-not that I'm not aware of.....
Solar is used by many homeowners and in some public installations but apparently it does not generate enough to compensate for broken and/or in maintenance oil driven generators.
 
Last edited:
solar installation is rather expensive here and the panels on rooftops are considered flying projectiles in hurricane-force winds, and at one point were not insured for winds over a certain mph but not sure if that is still the case. they are trying to get new construction to be 35% off the grid but most of the huge villas have generators, not solar. not sure where they would put a solar field and battery storage large enough to power the entire island ? Nuclear could be a solution but nuclear waste disposal is an issue - but France is a big proponent of nuclear power - over 70% of its energy needs I think...
 
My understanding is that two of the large EDF generators, G7 and G8 (8MW each), are down. The G8 generator is down for a month-long period of preventative maintenance, and is expected to return to service this week. The G7 generator failed and is being repaired, but I haven’t heard an expected completion date.

I’ve lost track of how many generators are in the EDF plant in Public. Total daily power usage is somewhere around 24MW, so there must be more generators than just G7 and G8, but likely with lower capacity.

There are a number (10+?) of smaller temporary generators which EDF has had shipped in, and which are placed in locations around the island. I don’t know details on the types and sizes of the temporary generators. If they’re Continuous or Prime Power then they’re designed to run non-stop for months. If they’re Standby Power then they’ll have different duty hour specifications and maintenance requirements.
Thanks for this review & explanation, Kevin!
 
Solar is used by many homeowners and in some public installations but apparently it does not generate enough to compensate for broken and/or in maintenance oil driven generators.
“. . . many homeowners”? Not my impression. What percent qualifies for “many?“ I’ve looked into solar. In addition to significant upfront cost (compared to US), there are numerous other factors affecting solar utilization — from installation costs (experienced, reputable people are sparse) — to safety issues connected to unfamiliarity of the systems among people working around them when they’re installed.
 
solar installation is rather expensive here and the panels on rooftops are considered flying projectiles in hurricane-force winds, and at one point were not insured for winds over a certain mph but not sure if that is still the case. they are trying to get new construction to be 35% off the grid but most of the huge villas have generators, not solar. not sure where they would put a solar field and battery storage large enough to power the entire island ? Nuclear could be a solution but nuclear waste disposal is an issue - but France is a big proponent of nuclear power - over 70% of its energy needs I think...
Windmills?
 
Just curious, with all the talk of new villas and electricity consumption and phased blackouts, I was under the impression that in the "good ole days" electrical service on the island was a bit hit and miss too. N'est-ce pas ?
 
Just curious, with all the talk of new villas and electricity consumption and phased blackouts, I was under the impression that in the "good ole days" electrical service on the island was a bit hit and miss too. N'est-ce pas ?
Yes but people didn't have the same expectations. tourists were fewer and far between and the locals - even those born in the late 50s early 60s - grew up without electricity or running water - until about 1970 in some cases. Rosemond says at the end of the day, he and his siblings got one bucket of water from the cistern - pull up the bucket by a rope even today - and splash each other - that was their "shower" after a day of walking to school from Flamands to Gustavia, playing soccer, swimming etc...when I first went to their house in 1991 there was no running water in the kitchen. Heated cistern water in a series of basins was how to do the dishes!

Oil lamps, candles and cooking with gas or over an open fire were the standards. Very few people had pools much less heated ones and the old houses were not air-conditioned. So if you are nostalgic for the good old days, be careful what you wish for...
 
*⚡ SAINT-BARTHÉLEMY: PROVISIONAL POWER OUTAGE SCHEDULE*

*📅 Tuesday, November 17, 2026*

Due to ongoing strain on electricity production, power outages may be necessary to maintain the balance of the electrical grid.

⚠️ This schedule is provisional. Outages are not systematic and depend on available production and the island's actual consumption.

📋 See below for the times and areas likely to be affected.

*🕗 FROM 8 AM TO 11 AM – SAINT-JEAN, LORIENT, EAST COAST, AND GUSTAVIA SECTORS*

• *Saint-Jean and Lorient Sector:* Lédée housing development, Super U supermarket, airport, La Savane shopping center, Saint-Jean main road, Les Sables shopping center, Vaval center, Les Amandiers center, Villa Créole, Les Jardins de Saint-Jean, Jean Barth residences, Espace Neptune, Coupe-Gorge road, Lorient Ti Fond, L’Îlot shopping center, and L’Oasis shopping center.

• *Lorient and East Coast Sector:* Lorient Centre Road, Post Office, Traffic Department, Monoprix, Jojo Burger, road to Petite Saline, Ligne de Saint-Barth cul-de-sac, vehicle inspection center, Morne Finistère, Pointe Milou, Grand Carénage, Mont Jean, Mono-Shop, Marigot La Cave and Marigot Bord de Mer.

• *Gustavia Sector:* Capitaine Bertin building, Carré d’Or building, À Vos Marques building, Pablo building, CPS, sub-prefecture, Colony Club, Couchant subdivision, Lubin Brin Street, section of Fahlberg Street before L’Ancre, Lurin Road, Pogammus subdivision, Chemin des Plateaux, Gouverneur Road, Andres subdivision and educational farm.

*🕚 FROM 11 AM TO 3 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol Road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau Road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Morne Tourterelle Road, and Grande Saline.

*🕒 FROM 3 PM TO 6:30 PM – TOURTERELLE AND MARIGOT SECTORS*

• *Tourterelle Sector:* Saint-Jean sports complex, Plaine des Jeux, territorial swimming pool, Route de l’Étang de Saint-Jean, Saint-Jean bridge, Saint-Jean heights, Petite Saline, Villon, Reyhan housing estate, Grand Fond, Toiny, Toiny heights, Petit Cul-de-Sac, Étang de Petit Cul-de-Sac area, Le Levant housing estate, Grand Cul-de-Sac heights, and Route de l’Étang de Grand Cul-de-Sac.

• *Marigot Sector:* STIS, morgue, gas station, shopping areas of Galeries du Commerce and Mangliers, Terrasses de Saint-Jean, Bon Coin, Camaruche, Carrefour Quatre Vents, Vitet, Dévé, Marigot-Vitet road, Grand Cul-de-Sac road, and Barthélemy road.

*🕡 FROM 6:30 PM TO 11:00 PM – COROSSOL AND GUSTAVIA SECTORS*

• *Corossol Sector:* Public (descent towards the beach), Corossol road, Grande Savane, Le Platon, Corossol, Corossol-Colombier ascent, Colombier, Hansen, Ti Morne, La Source, Flamands, Terre-Neuve, Merlette, Château d’Eau road, Anse des Lézards, Anse des Cayes, Quartier du Roy, and La Carrière.

• *Gustavia Sector:* Lurin, Grands Bois, Morne Tourterelle, Saint-Jean Carénage, Chemin du Morne Tourterelle, and Grande Saline.

_⚡ Let's continue our efforts to conserve energy!_

Everyone's cooperation remains essential to limit the risk of power outages, particularly by reducing the use of air conditioning and energy-intensive appliances.

EDF teams remain committed to maintaining the balance of the electrical grid.

_🙏 Thank you all for your understanding and cooperation._
 
“. . . many homeowners”? Not my impression. What percent qualifies for “many?“ I’ve looked into solar. In addition to significant upfront cost (compared to US), there are numerous other factors affecting solar utilization — from installation costs (experienced, reputable people are sparse) — to safety issues connected to unfamiliarity of the systems among people working around them when they’re installed.
It might be a question to ask the property owner association members at your next gathering, who has solar panels and batteries and whether they are out of or feeding the grid.
 